Report for Tuesday, August 7, 2001
Today we continued work on the roof and exterior walls and began installation of the heating and cooling duct work in the sanctuary area. A section of the roof and some of the walls will be delayed until we receive a replacement column for the one which is bent. The photos show the nearly one half completed roof on the west side, one of the duct sections, and a look inside the front door toward the north. |