Mountain Vista United Methodist Church
Daily Construction Diary
July 30, 2001

 

Monday, July 30, 2001

Today the remainder of the steel structure materials was delivered. The steel people installed more purlins, the members which will hold the roof sheeting.

The City crew completed the sidewalk along 3200 West except for spaces left for the fire hydrant line south of the driveway and the temporary driveway we are using for construction access. They will finish these when they come back after our utility work is finished.

Sprinkler Supply finished revisions to the sprinkler irrigation plan and it is ready for our use. The materials will be delivered with a one day notice to them.

The photos today show the completed sidewalk looking south, the driveway connection with part of the forms set, and a view of the steel structure showing the area where additional purlins will be installed for the roof support.


| Home | Worship | Sunday School | Youth | Music Ministry | Special Ministries | Prayer Room | Construction Diary | Committees | Joyful Sound | Newsletter | Calendar | Core Values |